ST. ALBANS CITY — After purchasing the Ralston building two years ago, the City of St. Albans is now preparing to move forward with renovations to the building this summer.
St. Albans City Council approved forming a limited liability corporation, or LLC, with an outside lender – identified as Peoples Trust Company in city documents – in order to utilize state and federal historic tax credits to cover roughly 30% of the renovation project’s estimated $1.3 million cost.
Once the renovations are completed, the city intends to bring the building to market.
Councilors approved forming the LLC after taking a tour of 45 Kingman St. Tuesday night. Developer Jim Cameron used similar historic tax credits when tackling the renovations of the former courthouse building, and he’s currently wrapping up the housing portion of the project while pursuing a potential business tenant for 45 Kingman’s first floor.
City Manager Dominic Cloud said the Ralston building would be a similar project, in that it would create market rate housing – one or two bedroom apartments – primarily for young professionals.
There is currently one apartment in the Ralston building. The renovations – as proposed – would bring the total up to eight.
As for the Ralston building’s first floor, Cloud said the space is currently outfitted as a restaurant after the city fulfilled its lease agreement with Nourish to help cover any refurbishment costs, and the first floor will likely retain that use moving forward.
Nourish, a vegan eatery and market, closed last summer. Owner Ric Lavallee said a lack of foot traffic and the non-mainstream focus of the business hurt the bottom line.
“It’s been repositioned in the market as a restaurant and it will stay as that,” Cloud said. “We envision selling (the building) to the operator of the first floor commercial business so that the residential units can provide some balance to the first floor business. That’s just the idea at this point. Right now, we’re focused on getting the new units created and bringing the renovated building to the market.”
Work for the upper floor apartments is scheduled to be completed over the next construction season, this spring and summer.
Other Franklin County projects that have used the state’s historic tax credit program include thehistoric Soule House in Fairfield, the Saint Albans Museum, 1901 Champlain Theater in Swanton, as well as 45 Kingman St. The Franklin County Industrial Development Corp. also used the state program to tackle renovations of Enosburg’s Perley Block.
With council’s approval to form an LLC, the city administration intends to seek out the historic tax credits, then return to council for the project’s final approval.
The City of St. Albans received close to $3.6 million of state-funneled American Rescue Plan Act dollars to address sewer overflows and stormwater issues. The combined total will help the city cover three upcoming water infrastructure projects, city planning director Chip Sawyer explained Tuesday night.
The three include a sewer separation project on Stebbins Street, an upcoming installation of an underground tank at Houghton Park and the creation of a gravel wetland southwest of Lemnah Drive.
The first two projects would help the city eliminate sewer overflows. Sawyer said $3.1 million of the state-approved funds would address ongoing issues with stormwater overwhelming the combined sewer system near the intersection of Elm and Lower Welden Streets.
The city has been pushed by the Vermont Department of Environmental Conservation to eliminate the overflows altogether, Sawyer said, and tackling the two projects – once completed – should help address a majority of the incidents by creating additional storage capacity while cutting back on the amount of water that feeds into the system.
The first of the projects – separating stormwater from feeding into the sewer system at Stebbins Street – would help reduce an estimated 66,000 gallons of water from flowing into the city’s sewer infrastructure during a 24-hour flood event. Installation of the new piping is expected to be completed over this summer.
The Houghton Park underground tank, however, is likely another year out before construction can begin. The project entails digging up the southern tip of Houghton Park to add a 500,000 gallon tank that can hold any major water overflow during a flood. Later, the water can then be released slowly to be treated over time.
The construction could provide some disruptions to the neighborhood next year as dirt is hauled in and out of the area to finish the project, but once complete, Sawyer said there will be little indication there’s a tank underground.
“There might be an extra manhole, but otherwise you won’t even know that it’s there,” Sawyer said.
The city still needs to complete the final engineering designs for the underground tank, but Sawyer estimates the final project cost to come in around $4 million. The state-funneled allocation of $3.1 million should help cover a large portion of those costs, and the city can also rely on state revolving funds to tackle infrastructure expenses.
Sawyer said the city will likely also need to seek out a bond to cover any remaining costs related to the sewer-related projects, which would be funneled down into customers’ sewer rates.
The last of the three water projects involves a stormwater abatement project west of Lemnah Drive near Stevens Brook. The city received roughly $500,000 in ARPA dollars to help tackle its stormwater obligations to the state, and the installation of a gravel wetland near Lemnah is the first of the city’s mandated stormwater projects in order to reduce phosphorus run-off into Lake Champlain.
Sawyer said construction of the man-made wetland – passersby will see a mix of stone and plants combined in a way to filter out phosphorus – is slated to begin in the summer of 2025. The city has until 2026 to spend the state’s ARPA dollars.
“It’s good to finally be getting to this point of building projects and fulfilling obligations,” Sawyer said.