ST. ALBANS CITY – The City of St. Albans has a short ballot for Town Meeting Day this year, featuring uncontested races for three seats and a relatively non-controversial budget.
Article 3, however, continues an ongoing effort to complete the city’s water tank upgrades. Here are the details.
Article 3: Water Tank Refurbishment
“Shall the City of St. Albans issue general obligation bonds or notes in an amount not to exceed $1,600,000 for the purpose of refurbishing the Congress Street water tank, the total estimated cost of such improvements being $1,600,000, with reductions of $800,000 anticipated through grants and debt forgiveness from the state and federal governments, and said bonds to be paid by the users of the water system?”
Efforts to upgrade the city’s water storage systems began back in 2018 when state inspectors discovered the city’s old tank, built in 1953, needed upgrades in order to last another two decades. But first, they needed to ensure any repairs wouldn’t disrupt water service.
City officials followed up with a plan to build a new tank, expanding on storage capacity and tackling requirements around system redundancy, and in 2023, the city passed a $2.3 million bond vote to cover construction of a new 1.2 million gallon tank, which was finished later that year.
Now, with everything in place, the old tank is ready for its refurbishment.
To cover costs this year, the city is asking residents permission to borrow half of the $1.6 million cost, with the other half to be covered by a 40-year no interest loan coming from the Drinking Water State Revolving Fund.
As for the actual project, public works director Marty Manahan said refurbishment will include emptying the tank, sandblasting the interior and exterior and making any repairs to ensure the tank lasts. The city also expects to install a mixer in the new tank to keep the water moving.
Once the repairs are made, the upgrades should make the tank ready to be used again up to its full 1 million-gallon storage capacity.
If voters pass the ballot article, Manahan said the plan is to start the tank’s rehabilitation process this summer, which would keep the tank offline for roughly two months. For residents, there will be no interruption in service, nor much disruption in the neighborhood caused by the refurbishment process.
As for the color, Manahan said the city will likely look to keep it roughly the same color as the new tank – a forest green.