Enosburg Falls village trustees move ahead with quick fix on Kendall hydro

Posted

ENOSBURG FALLS — Village trustees selected the quick-fix option for the downed Kendall hydropower unit. 

Trustees sent a unanimous vote Nov. 10 to review the roughly two-month solution. If there’s no problem, the village will move forward. Trustees did, however, add a caveat that repairs be completed in a timely fashion “not to exceed January 1st,” after learning what the utilities could be missing out on in revenue during winter. 

Village electric crews discovered the downed hydro in June. Following inspection, they learned the unit had an issue in where a lower bearing unit failed. 

The cost is in the ballpark of $18,000 and $20,000, village manager John Dasaro said. The village will likely have to finance the repairs. 

“I think we should get the ball rolling on the quick fix, personally, get the thing running, get some income production going on,” trustee Chair Eli Gabuzda said. 

The quick fix essentially sets the blades to be open to certain fixed angles. Fairbanks Mill, a hydroelectric construction company, recommends an angle which produces about 25-to- 30% electricity production. When the hydro is working correctly, the blades can be adjusted with the flow of the river to keep producing at all times. 

The Kendall is one of two hydros the village owns which produces power for some 1,800 customers. According to the village’s director of finance, Caroline Marcy, the Kendall plant makes a little more than half of the electricity generated. 

“So not only would you be losing 60% of your generation if you keep the Kendall down, it’s also going to affect the Village (hydro), so you will lose even more than that,” she said. 

Using data from the past few years, Marcy said December and January are the biggest revenue times for the electric department as people use more devices to keep warm in winter. Last January netted the village almost $77,000 alone. 

The numbers, she said, will show the price of indecision from the trustee board. What’s not being produced, the village has to buy at market rate. 

“You’re losing by not having it generate by that much,” Marcy said. 

The other aspect to think about, Marcy said, is timing. If the fix can be done within a short period of time, it can pay itself off, rather than going months without the revenue. It could be more economical to do the quick fix, and then also come back for a permanent fix down the road. 

As for how long the quick fix will last, Dasaro said it’s like fixing an old car. Fairbanks Mill will guarantee their own work and it’ll run as best it can. 

Trustees first started weighing their options back in August when they learned of three options to fix the hydro. The first option is the quick fix, the next was to restore the unit to its pre-failure condition costing about $100,000, and last was purchasing a unit which would run a bill of about $800,000. 

The new unit is more of a long-term plan, Vice Chair Jason Longway said, closer to a 5 or 10 year plan. 

“I do think we should have a good plan moving forward on making it temporary instead of sitting on it after it's done,” he said. “‘Oh it’s still working,’ no, I want to make sure there’s a good plan.” 

Dasaro will meet with Fairbanks and the electric department crew to gather a time frame for the fix.