SWANTON VILLAGE — The Village of Swanton is looking to add a new public safety building and update its space, and it’ll be up to voters this March to decide if they agree with the move.
The village administration purchased the property abutting its municipal building last April for $400,000 to secure a site for the new build and move forward with a major expansion of the village’s available space.
Village Manager Bill Sheets said the effort is necessary for a 42-person staff that’s outgrown its 48-year-old building, while providing the municipality with the opportunity to modernize its fire and police departments.
“There’s a lot going on under one roof,” Sheets said. “The root cause is we are bursting at the seams, we are unable to grow appropriately in our current space.”
To accomplish the proposed plan, the village is asking for $19.9 million in bonding authority, which would potentially add $457,000 in annual taxes potentially split between village and town residents. The village currently operates a $13 million budget due to its enterprise utility services.
Village department heads spent a few long days this past December talking to residents about the village’s need for space during multiple informational open houses that extended into the night. During the presentation, residents got the chance to ask more questions about the proposed plan, as well as get a firsthand look into the lack of space the village is currently dealing with.
Here’s a breakdown:
Out of the five departments currently residing in the Swanton Village Municipal Building, the police department’s need is likely the greatest as the law enforcement agency currently occupies three rooms totaling 600-square feet of space. Inside the limited interior, the eight-member department houses its administrative offices, holding cells and a portion of its evidence locker.
A new public safety building, however, would allow the police department to expand into 6,000 square feet to better accommodate its operations. It would also allow the department to utilize the amenities provided by a 21st century building, such as a secure sally port for police cruisers, an expanded evidence locker, dedicated holding cells (one specialized for juvenile arrests), an interrogation room, armory and a front secure room where the public could meet with staff.
“The building that’s proposed I’m going to stress is not extravagant,” Chief Matt Sullivan said. “ … but it would meet the needs of the community for the next 50 years.”
A shared 4,000 square feet of space – where meeting rooms and bathrooms would be located – would also be used by both the police department and fire department.
“We’re well aware that we’re asking a lot, but if you want to create a vibrant community, it must start with public safety,” Sheets said.
With a successful vote, the village could then move onto its next phase with the department – regionalization. Citing calls from neighboring town residents looking for more police coverage, Sheets said the new building would set the Swanton Police Department up to expand its patrols into abutting communities.
Of course, there are some inherent risks for village residents. The majority of the initial financial impact of covering the building’s debt burden – $457,000 per year to pay down a 30-year bond at 4.5% – would largely be covered by village property taxes in the first few years. Sheets said the portion paid by village taxpayers could be reduced, however, if neighboring communities jump on board and create long-term contracts with the department for more patrols.
Enosburgh and Highgate, specifically, are both actively looking for additional police coverage. Highgate’s contract with the St. Albans Police Department is lapsing this summer as the city department prepares to fulfill an earlier contract signed with the Town of St. Albans, and in Enosburgh, a reduced contract with the Franklin County Sheriff’s Office pushed town officials to seek out additional law enforcement patrols this past spring.
By picking up long-term agreements with such Franklin County towns, Sheets said the building’s tax burden could then be extended over a wider population to the point where village taxpayers’ costs to run the department would be reduced.
There’s also a question of what Swanton town residents will do, as the town is considering expanding its contract with the village’s police department. With a public hearing on the calendar set for Jan. 10, the town selectboard is looking to hear from town residents before making a decision, but the current consideration is whether residents are interested in expanding to 70-hour per week patrol coverage, up from the current 56 hours received per week.
Town residents will then get a say during Town Meeting Day in 2025 if they’d like to go with full-time coverage, thereby splitting potential costs down the middle with the village if approved.
“That’s really at the heart of the issue right now, until we decide that we can’t even give a proper answer to the village proposal,” Town Selectboard Earl Fournier said during the board’s Dec. 19 meeting.
At 70 hours per week, town residents would be on hand to cover a third of the police department’s portion of the bond costs, and any tax help covering the project’s debt burden would be built into any expanded contracts made with the village.
Administrative staff and the public’s entrance into the building wouldn’t see any substantial changes outside of a general expansion into the space where the police department is currently operating out of. Sheets said the space would be rearranged with a few walls, and there would be enough room to where customers could meet with staff on a one-to-one basis if a discussion – such as those over financial debts – would be better conducted in private.
The outside walkway into the building would also get covered to prevent ice and snow from causing potential falls or other mishaps.
Assistant Fire Chief Dan Chevalier provided the rundown on the current needs of the Swanton Fire Department, which would be able to provide better safety practices to department volunteers with additional space.
The department – consisting of 28 volunteers and six apparatus – resides in the municipal building’s southern end, with six truck bays and a handful of offices housing department business.
Chevalier said the new building, however, would open the space up around dangerous large equipment, eliminate chokepoints and provide better workflows to keep volunteers away from dangerous chemicals.
“What this building does is it takes care of all the deficiencies we have now and gets us back up to where we probably should have been for a while,” he said.
Since the building was initially constructed, Chevalier said the fire industry’s understanding of harmful chemicals, as well as the presence of more carcinogens in today’s building materials, has changed what firefighters need to do to keep such toxic substances away from their skin and lungs.
Right now, the fire department does have a specialized machine that washes firefighting gear, but more space would allow the department to purchase another to speed up the process and allow firefighters to reduce their exposure to such chemicals.
Chevalier said the need to reduce that exposure will most likely increase as the use of electric vehicles increases, as they burn longer with more dangerous chemicals.
As for more space in the truck bay, the new department is designed to have an entrance and exit on opposite sides of the building, helping the department to reduce its response time, and the design will provide better airflow so the truck’s exhaust won’t linger in the garage after volunteers return from a call.
“We’re at a 350% increase in call volume since the building was built,” Chevalier said.
Once the fire department moves out of its current space, the public works department would move in, stretching its legs so it could store more equipment inside and make maintaining it a more efficient process.
“It’d be nice to bring a truck in and walk around it and clean it without pulling them out,” public works foreman Dean Ryan said.
As Ryan explained, the department is already overpacked as it is, so workers will keep some plow trucks outside during the winter, and getting the vehicles’ diesel engines started can take some work, adding hours or even days to a task that could be solved with more storage space.
Just getting inside the vehicles can be a challenge, too, as workers often have to maneuver around dangerous equipment, like plows. Ryan said some people who toured the building labeled the public department’s space issues as a “smokeshow” but the limited space does make regular maintenance much more difficult when staff can barely get a good look at a problem.
The police department also uses a section of the public works space to store a few larger items. Sullivan said officers will bring evidence through the public works garage to another evidence storage locker – quickly running out of room – located in the unfinished portion of the building’s second floor. With strict rules around chain of custody of evidence, it’s not considered a best practice, Sullivan said.
When updated, Sheets said the public works space wouldn’t change much outside of knocking out a wall on the building’s southern end to join it with Missisquoi Valley Rescue, which is moving into the neighboring property.
A wall would also be built to separate the public works bays from the break rooms of village workers to help improve air quality in the space.
Out of the five departments, the village’s electric department would see the least change. Like the public works department, the electric department would expand outward as the fire department vacates its current space, providing more room to store electrical equipment like transformers that are better left inside.
If village voters move forward with the proposed $19.9 million bonding authority as proposed by the Village of Swanton, the resulting tax rate for 2025 for policing would be .8195. Without the bond, the operating costs alone of the Swanton Police Department would be .6355, as proposed.
For a $300,000 residence, the lower tax rate of .6355 would result in a $1,906 annual tax bill to cover Swanton Village police costs. The additional bond payment in 2025, if approved, would bring that bill up to $2,458.40.
As early as last year, the same village taxpayer would have paid $1,537.20 to cover operational policing costs.
Because the public safety building also includes the fire department, there’s also a tax increase associated with the fire department operations, although it’s mitigated by a larger tax base due to town residents already helping cover costs.
For village residents, the additional bond payment to also cover the fire department portion of costs would add just over $300 to the year-over-year tax increase, setting the total year-over-year increase to public safety costs for a village homeowner with a $300,000 residence at $958.34.
Sheets said the numbers as proposed would be a worst case scenario for the village, dependent on future contracts, future grant opportunities and potential loan forgiveness that could reduce total costs.
As for timeline, Sheets said the building could break ground as early as September or October if bonding authority is approved by voters this March. The construction would then take roughly a year to 15 months before completion.
The village would also have to take care of a few administrative tasks before they can wrap up the project. The property, for example, would have to be annexed into the village because it’s technically in town limits.
Overall construction of both the building and refurbishment would also add a connected geothermal system to heat both buildings to save on electricity costs, and stormwater improvements would need to be added to the property’s periphery to meet state restrictions on impervious surfaces before the entire project is completed.