SWANTON VILLAGE — Swanton Village voters approved a $7.5 million bond to construct a new electric department building on Tuesday, May 6, during a special election.
The final vote in favor of the bond was 148 to 73.
Tuesday’s count was the second vote taken by Swanton Village regarding the project after voters rejected the first electric department plan by a margin of six votes this past Town Meeting Day.
Swanton Village Trustees, however, moved forward with the request for a second vote not long after recognizing the project was needed to solve the village’s ongoing space issues. Between votes, trustees also scrubbed another roughly $1 million from the bond request to make the expense smaller for ratepayers.
Swanton Village can now move forward with the build.
The Swanton Village vote on Tuesday was the culmination of at least two years of planning work undertaken by village officials, and with voters’ approval in hand, they now have the runway to get moving on the project.
The vote itself gave the village the needed authority to seek out a $7.5 million bond to build an electric department facility. Village Manager Bill Sheets said now the village will work with the Vermont Bond Bank to secure the funds while also preparing the site and finalizing the building’s plans.
The proposed site of the new building is already owned by the Village of Swanton. To be located at 124 First Street, the village purchased the site back in 2024 for roughly $400,000 by utilizing ARPA funds.
To use it for the new build, though, the village will have to clear it of any materials that could cause environmental contamination. Sheets said the village is looking to take advantage of the Petroleum Cleanup Fund to get it done as an old 2,000 gallon storage tank was found on site.
“So we’ll have to take that out,” he said. “This is a fairly easy remediation.”
Carroll Concrete had owned the land prior to the village’s purchase.
Meanwhile, village trustees will also be working to finalize the build’s plans by matching up the proposed footprint with the granular details needed to actually construct a facility. Sheets said the team of village officials, village trustees, architects with Wayman Lamphere and builders with Connor Contracting will continue to refine the plans until all of the project’s moving pieces line up. If everything goes forward smoothly, construction could begin as early as the end of 2025, although next spring is more likely, Sheets said.
Once the building is finished, the village would then be able to move administrative staff and electric department workers and rearrange the municipal building’s existing space to make more room for the Swanton Village Police Department.
At that juncture, likely years down the line, Sheets said his office would become the police chief’s, the building’s fireproof records vault would become a secure evidence locker, and the electric department workbays would be transformed into a sallyport.
Now that the bond vote passed, village officials will also be approaching the Vermont Public Power Supply Authority to review its electric rates. The state agency regulates rate fees and changes, and Sheets said the village will need to go through an extensive review process with VPPSA to understand the overall operational impact of the $7.5 million bond.
VPPSA will then decide what the final rate will be. Sheets said they’ll likely begin that process six to nine months from now, although ratepayers won’t likely see any impacts until at least 2026.
As for any impact on property taxes, the village worked hard to ensure that the new building would only affect how much people paid on their electric utility bills.
The project’s initial pitch — rolled out last year — had been to create a public safety building to make more room for village employees after the municipality outgrew its 50-year-old facility.
The price-tag and resulting public conversations in 2024, however, shut down that gameplan. The first bond request to create a public safety building ended up defeated at the polls during Town Meeting Day that year.
Voters also replaced longtime trustee president Neal Speer with David Winchester, who had been critical of the original project.
At the time, village voters had expressed pushback against the project’s impact to property taxes, and the new trustee board pivoted to creating an alternate electric department building project that would rely on a larger pool of ratepayers instead.
Voters, however, ended up defeating that proposal as well during Town Meeting Day 2025. At the time, village officials were expressing concerns that voters had focused so strongly on the public safety building that it was difficult to get information out about the new-and-improved electric department project.
After Tuesday’s results, it seems trustees had found a way to connect with enough voters who supported it to succeed on the second attempt.
Village Clerk Dianne Day said Tuesday afternoon there hadn’t been too many people coming by to vote throughout the day, but there was a notable difference in people’s approaches to the topic, with more people expressing positive views than before.
Day said the village’s efforts could have helped. For example, about 70-or-so votes had been submitted by absentee vote, and Day said they had sent out a mailer to help get more people on board.
“(The project) has been better received,” Day said. “I’ve heard a few people say verbally that this is affordable. I’m feeling positive.”