ST. ALBANS TOWN — After Wednesday, the Town of St. Albans is one step closer to installing a walk/bike path alongside Route 7.
Town planning officials have been pushing the project forward over the last few years, but a meeting held to hear public concerns Wednesday night helped clarify the potential difficulties that could come with installing a path along that route.
“We have a livability study that identified, ‘Yeah, we need it,’” community development director Megan Sherlund said. “This (study) is identifying where it makes sense. The next steps are going to be to secure funding to get it designed and permitted, and then the funding for the construction will be the biggest feat.”
Following a review of the data, project engineers recommended the best way to add a route is to extend one along the route’s east side before crossing the road near Highgate Commons and continuing on the west side until the Swanton line.
The final route, however, is yet to be determined.
After hearing from residents Wednesday night, planners expect to incorporate the feedback received into the project’s next iteration, with actual construction likely being years down the line.
To examine the route, town officials ended up hiring civil engineering firm VHB to help coordinate an alternatives study and examine the route.
And for the most part, it seems that the path should have adequate clearance to stretch along Route 7’s northern corridor, project manager Drew Gingras said.
“As we continue north, we’re looking at – what is access to businesses like through these areas? Are there a lot of driveways? Are there a lot of intersections?” he said.
One of the biggest challenges was trying to figure a way to cross the intersection with state Route 207 where heavy traffic occurs. Gingras suggested moving the pathway to the west side before reaching that area, which would help walkers and bicyclists access Walmart.
“Both alternatives kind of had equal desirability rankings, but the transition here avoids that 207 interchange,” Gingras said. “We saw that as the best option for walkers, bikers and drivers.”
Under the plan, crosswalk intersections would be incorporated at the two stoplights that currently stop traffic along the route closer to Interstate 89.
Gingras said the town will also likely need to coordinate with some of the businesses located closer to the City of St. Albans during the design phase. A few of the buildings located there (including the Saint Albans Messenger building) have exceptionally wide driveways and could use a change.
Re-tailoring some of those exit and entrance points could help with traffic in the area, but the town would likely have to work out the best approach that wouldn’t hurt business.
While Gingras explained the details behind VHB’s engineering work, those in the audience mostly had concerns about the project itself. While a few people spoke in favor of adding a shared use path along Route 7, many commenters expressed concerns, asking about traffic counts, raising questions about E-bike riders, highlighting potential disruptions to business and asking if people will even use the path.
“There were no counts done, generally speaking on something like this where there are limited or no facilities,” Gingras said. “Those are often seen as not terribly useful because the fact is, this is a hostile environment to walk and bike in. There’s probably not a lot of people doing it. … If you remove that hostility, those numbers are going to go up.”
A few attendees also expressed the need for a future retooling of Route 7 itself, asking for more lanes to help address traffic concerns. Since the end of the pandemic, it’s not uncommon to sit behind a vehicle waiting to turn left while driving along Route 7, especially as more and more business momentum has concentrated itself around the well-traveled roadway.
Gingras explained the shared used path study didn’t go into those details, as the bounds of the study focused primarily on making sure that it would be possible to actually incorporate a shared use path along the right-a-way without major disruption.
And if the project did end up moving forward, he said construction easements would likely need to be permitted, although there would be no permanent easements necessary.
Sherlund also explained to attendees that while this project didn’t go into traffic counts, the town is examining the overarching travel patterns as officials continue their work on the transit-oriented development study, which had its own public informational meetings this past fall.
“We have to see that need and hear those people that don’t come to these meetings,” Sherlund said. “If they live on the north side of the city, it’s hard for them to get to Food City or other smaller convenience grocery stores. So they’re taking their lives in their hands to walk down to Hannaford, or Price Chopper.”