New housing on horizon?; 80-unit subdivision gets review from St. Albans Town

Posted

ST. ALBANS TOWN — Plans to create roughly 80 more units of mostly single family homes on St. Albans Town’s south side started moving through the local development review process last month.

Presented by project engineer Sam Ruggiano and lot owner Alan Bourbeau, project developers are looking to cut up a 43-acre parcel used as agricultural land in order to create 80 units of market rate housing at the far end of Prospect Hill Road.

“We’ve gotten most of the sign-offs that we need for the Act 250 permit at this stage,” Ruggiano said. ”Now, we’re at this point of doing design, of doing traffic studies and coming to the (development review) board.”

Housing on the horizon?

As Ruggiano explained, developers have spent roughly the last year pulling together state permits and approvals to answer questions that come out of the Act 250 review process, and at this point, they’re starting to put more substantial plans on paper to map out the 43.4-acre parcel.

Documents submitted to the development review board show the sketch plans of how developers would divide the plot — currently owned by dairy farmers Bourbeau & Sons — in order to prepare for a subdivision. The actual buildout of houses would be completed, in theory, by a third party. 

Ruggiano said they’re aiming to create enough space for roughly 80 units, although the exact property lines still need to be finalized. Depending on how things shake out, they’re considering whether to pair a few plots to make them into bigger duplex properties. Either way, developers would need to aim for roughly 80 units to make the math work out.

Project documents estimate the infrastructure buildout work will cost roughly $2.8 million to add all necessary improvements required to put houses on each lot. If all goes according to plan, construction could begin as early as 2027. If price trends continue, Ruggiano estimated the cost for each home would be close to $400,000.

“This is the first step in a long process,” he said.

As for the subdivision’s water source, developers are looking to tap into St. Albans City’s municipal sewer and water as a line near the property meets the minimum pressure requirements.

To ensure that the municipality could provide water in the area, Ruggiano said he’s been in steady communication with the City of St. Albans, especially in regards to fire protection and hydrant placement. Stormwater improvements are also expected to be built out to create a closed system to treat any water coming from the property.

Approved with conditions

During the development review board meeting held in December, both board members and public residents looked at ways to mitigate any major impacts that could be caused by the new subdivision. 

Many neighbors in the area expressed concerns about additional traffic caused by a development at the end of Prospect Hill Road, especially as the road itself is narrow and lacks sidewalks. 

Residents also had questions about space. Developers are leaning on state-allowed lot sizes that are typically smaller than the average St. Albans Town single-family home, and a few neighbors expressed concerns about changing the character of the neighborhood, or had questions about how new residents would use space.

To help answer those concerns, the development review board ultimately approved the sketch plan review application with conditions, asking that a traffic study be completed and that developers work with the town to find ways to abate the influx of new residents in the area by creating new access points to the subdivision, or widening the road.

As part of its review, the board also asked the applicant to include some community/shared/green space for residents, to be represented on the sketch plan in future iterations. Before getting local sign-off, developers will need to go before the local board for a final site plan review in order to greenlight construction.