ST. ALBANS CITY – The City of St. Albans began construction of a 500,000-gallon underground storage tank in Houghton Park on Lower Welden Street this month to help cut down on flooding.
According to city officials, the project is intended to reduce the majority of periodic overflows of its combined stormwater/sewer system into Stevens Brook as well as flooding events in the intersection of Lower Welden Street and South Elm Street.
To complete the work, city contractors will excavate the southern area of Houghton Park along Lower Welden Street and install concrete sections to create storage chambers. The storage chambers will then take in stormwater/sewer overflows during major precipitation events, in order to pump the water out later for regular treatment.
Construction is scheduled to last through most of 2026.
Once completed, city officials will then cover the tank, later restoring Houghton Park to a lawn, except for the addition of some new hatches and vents. The existing courts for basketball, tennis and pickleball will not be affected.
While construction is ongoing, there may also be some impacts on surrounding streets such as periods of flagged one-lane traffic and shifts in pedestrian walkways.
As for the project’s cost, St. Albans city residents voted last year to approve a $4 million loan required for the buildout, with the total project cost estimated at $6.8 million. The funding stack includes federal dollars via the state’s American Rescue Plan Act program, the voter-approved loan and a Vermont Sewer Overflow and Stormwater Reuse Municipal Grant, administered by the Vermont Department of Environmental Conservation.
S.D Ireland is the lead contractor on the project, and Aldrich + Elliott is the lead consultant for design, engineering and monitoring.
According to city officials, this project is one of many that the City of St. Albans will have to construct in the coming years to tamp down on overflow incidents. For example, the last overflow that spilled water into Stevens Brook happened just this past December, as tracked by Vermont’s Agency of Natural Resources.