Georgia’s public works department to replace Mill River bridge next year

Posted

GEORGIA – In 2026, Georgia’s public works crew will be taking on bridge replacement work for Mill River Road to save some money for the town.

The selectboard gave a thumbs up for DPW to do the work and for materials to be purchased and stored until the 2026 start date. Switching to the public works department will have the town land far under budget.

With construction happening internally, the project’s engineer Tyler Billingsley of East Engineering PLC said the project’s expenses would come out to a rough estimate of $750,000.

The cost does not include Billingsley’s fees, price of an archeological dig commissioned earlier this year, labor prices or needed town equipment during construction.

“That follows, normally when towns take on projects themselves, it’s pretty typical to see 20, 30, 40% savings over a third party contractor,” Billingsley said. “We did add a bit of contingencies like any normal construction project, stuff pops up you are not ready for, didn’t account for, so we did add about 10% contingency just for other stuff that could pop up.”

The estimated cost comes out well below the approved $1.5 million bond voters agreed upon at Town Meeting last year.

Because Billingsley used current cost estimates, which rapidly increase the longer the selectboard waits on the project, he recommended allowing public works to gather up the materials and store them until construction gets underway.

Although the selectboard leaned into the savings, they asked public works director Todd Cadieux if the members of the road crew were able to do the bridge construction on top of their regular duties.

Cadieux said if the crew was able to work a little overtime they could get everything done. Roadside mowing for example, might be shifted into an after-hours activity.

“If it was a couple days they had to stay instead of hiring on a part-time person or I don't know if you want to consider going out to bid for the year,” he said. “I think it would be very expensive based on the amount we mow and the amount of cemeteries and stuff.”

A bridge of delays

Replacing the Mill River bridge, which crosses the Rugg Brook, has been in talks for years.

A 2008 study found damage in need of repair, and in 2013, a stormwater management plan reported the bridge was nearing “the end of its useful life.”

In 2021, the selectboard began discussing its steep price tag. According to officials at that time, the town was $900,000 dollars short in funding for the project.

Those costs were what forced the town to return a highway structures grant which would only cover a fraction of the replacement price.

When voters went to cast their ballot on the $1.5 million in 2024, town officials said the bridge was sinking a bit into the Rugg Brook gully and needed to be widened.

When plans finally started getting underway, the town ran into another issue. During the permitting process in February, the project was required to have an archaeological evaluation of the dig. The ground needed to thaw first, delaying the original 2025 construction date to next year.

Digging and construction is now set to happen in 2026, with public works completing the job to keep the town under the bond amount. The selectboard will have to decide what to do with the leftover balance.