FAIRFAX — According to engineers at Aldrich & Elliot, Fairfax may have one of the last operating aerated lagoon wastewater treatment facilities in the state. The selectboard is considering how to modernize it.
It’s been a year of discovery and fixes for the town and selectboard alike, and options for upgrading the system finally hit the board’s table Oct. 14.
“You’re looking at doing a $2.4 to $2.5 million dollar project versus a $4 million project at your plant, both with pros and cons,” managing engineer Jeffrey Lewis told the board. “That’s kind of the base question as far as what does the town want to bite off at this time?”
Selectboard members are taking more time to chew on the information and get more information from town staff before they make a final decision.
Fairfax has around $2 million already put away thanks to past efforts in securing dollars from Congressionally Directed Spending and American Rescue Plan Act monies. The price, however, keeps rising. When Town Manager Mike Bishop talked with Aldrich & Elliot in July the higher-end price was closer to $3 million.
While the town has a good amount of money saved, Bishop said he will also be looking at other grants and opportunities like the Community Housing Infrastructure Program to help offset, or outright pay for the infrastructure work.
Regardless of the plan the selectboard chooses, Fairfax will likely have a bond vote in the future.
The town’s current wastewater system uses an aeration lagoon where affluent enters the water, gets pumped full of oxygen and then spreads through three ponds where the process repeats with a few extra cleaning steps before emptying in the Lamoille. The entire process takes around 30 days.
Lewis offered three alternatives to the board ranging in price.
The first option, though not really do-able, is to add on a fourth lagoon to the treatment center. The town does not own all of the land needed there, and permitting would be near impossible as it falls within the floodplain.
Option #2 includes changing from the lagoon process to an extended aeration plant, otherwise known as a package plant. Extended aeration does much of the same work, but shrinks down the footprint of the system and adds a bunch more air, Lewis said.
Benefits of extended aeration include fitting the same treatment capacity of a lagoon in a smaller space, having a more active sludge management process for predictable budgeting and a flexible capacity for future growth. But it comes with a heftier price tag. Construction costs alone are estimated to be about $2.35 million.
This option is most preferred by the town’s contracted utility supervisors Laramie Water Resources.
“I would ask you to please carefully weigh option number two,” president of the company Phil Laramie said. “It’s new and shiny. I know that’s probably what everybody’s thinking, but from a flexibility standpoint, as an operator … we can run half the plant, save half the energy. As we grow, we can add more components into this. Flexibility-wise, operational-wise, budgeting-wise, being able to ship a small portion of sludge weekly, monthly, we can manage it way more closely so that we’re getting the best bang for our buck.”
Lastly, the middle-ground option is to refurbish what the town already has and add additional aeration. Though preliminary construction costs are estimated at $1.1 million, Fairfax would need a slight expansion of the control building, additional electrical work and more expensive sludge maintenance would remain in place.
The wastewater treatment facility sitting off Hunt Street was built in 1980. Since then, it has had one minor refurbishment in 1997. A lot of the equipment housed in the facility is sitting from the 90s refurbishment or are original pieces from the 80s.
“The main problem that you’re trying to address right now, is the age of the equipment itself is at the absolute end of its life,” Lewis said.
Wastewater equipment is expected to have a 20-year lifespan.
“You guys have achieved that goal with anything that was replaced in 1997,” Lewis said.
Since the work from the refurbishment, the town has done a few studies on the wastewater facility, but nothing has come into fruition over the years which has pushed upgrades further and further down the line.
In 2007, the town hired DuBois and King to study adding a fourth lagoon. Similar to the first option proposed, it would’ve expanded hydraulic and organic capacity in the town, but came with its own problems which led to it being shelved.
Thirteen years later, in 2020, the town was back and worked with Aldrich & Elliot for a 20-year evaluation of the system. Inspectors found age-related needs and Biochemical Oxygen Demand — a measurement of organic pollution and wastewater treatment effectiveness — at high levels. The proposed upgrade would replace aeration in the existing lagoons, but keep the existing footprint.
The current make-up of the system is one of high stress.
Organic waste being sent to the wastewater treatment facility has been above the designed loading capacity for years, Lewis said. Fairfax is in compliance with its permit limitations for water quality, but it’s taking a toll, Lewis continued, and it's something to be concerned about.
“Your building was originally constructed in 1980 with no additional work really completed since its original construction,” Lewis said. “In order to comply with permitted limits in recent years, the town has come up with some pretty creative solutions, and one of them is by throwing an additional electrical breaker and aeration unit in that front lagoon.”
The facility was never designed for the amount of electoral load being used, which has caused it to have 14-to-15 trip-outs alone since Laramie Water Resources took over, Lewis said in talks with the facility’s supervisor. Consistent electrical failure can create more trouble in the system.
Sludge produced from the lagoons is also a process adding up for the town. The clean-up work from 2025 didn’t make a dent, or was not done correctly, Lewis said. Sludge cleanout is supposed to be a routine maintenance item every 10-to-20 years.
“I just don’t think you should count that as a sludge cleanup,” he said.
From data put together over the month of September, Lewis said the system was holding on to 185 dry tonnage of sludge or about 20% of the lagoons.
Fairfax should be looking at a sludge cleanout in the next year or two. Sludge cleanup can happen during the upgrade construction, if timed correctly. Cleanup itself is a $405,000 cost, Lewis said.
Selectboard members also recently received a round of updates regarding the water system.
The water booster station on Buck Hollow Road will need to be relocated from its current location due to insufficient pressure in the pumps. One option is to move the pumps near the town office. Bishop said the move will come with a bit of a price, but the town is currently in talks with an engineering company to get estimates.
“The current booster does not meet current engineering or past engineering practices,” Laramie said. “Either we move or are forced to move it. We’ll be forced to move it in the next couple years, I don’t see it passing the next inspection in its current location.”
Laramie also gave an update to the test well the selectboard approved in August.
Permits are signed, and neighbors have been talked to, and Laramie said they’re optimistic about being able to drill a hole in the ground before the frost settles. The town is on step 4 of 10 he said.
Lastly, selectboard members gave Bishop permission to begin talks for a new contract with Laramie Water Resources. The water company took over management of the town’s utilities last December and the contract runs out later this year. Bishop is looking to offer a 5-year contract to the company, pending negotiations and selectboard approval.
“Where we started and where we are now, I’m very happy,” vice chair Kurt Magnan said. “A lot of work has been put into the system by you guys. I think it’s only fair to continue that relationship going forward.”