FAIRFAX – Fairfax’s selectboard received a new round of updates on the town’s water and sewer utilities Monday, including costs for two capital projects.
The two projects, a generator and a well operation, total $418,416.30 and are meant to boost the utility’s abilities until a larger renovation project can be completed. The projects are recommended by the town’s contractor, Laramie Water Resources. Both projects can be funded due to approved budgets in the new fiscal year and a line of credit the town has taken on.
The water and sewer utilities have $287,564 in the bank, a little more than half of which comes from certificates of deposits recently redeemed.
“If everyone remembers back in March, we talked about how we weren’t going to have any money by July 1,” Town Manager Mike Bishop said. “If you look at the numbers, you’ll see why we weren’t going to have any money, but with the new budget and line of credit, we’re able to [take on these projects].”
Meant to boost electrical capacity in Fairfax's water facility, the generator comes in at $105,550.
The town’s finance manager, Krista Smith, recommends using money from the certificates of deposits to fund the generator project in order to minimize the town’s need for additional borrowing.
Fairfax’s well water project comes with a heftier price of about $312,866, though the town is only responsible for $120,000 upfront and will be reimbursed once it wraps up. The plan is to get a test well drilled in the next 12 weeks, Bishop said.
“That is a project that will be reimbursed after completion, so we receive the invoices, we pay the invoices and then once it's done we can submit the invoices and get the money back,” Smith said.
Smith recommends the town use the line of credit currently assisting with water and sewer capital costs to fund the upfront payment. Because that expenditure is meant to be reimbursed, Smith said using a line of credit won’t hold up cash the town has available on hand.
Altogether, the town does have enough cash to fund both projects out of pocket, however, Smith recommends against doing so because it would significantly diminish available cash in reserves and operational expenses.
“We don’t want to do it because it ties up funds to pay for the bills that are coming in,” she said. “Right now, technically, water and sewer owes the town $89,000, I believe it is, for costs and if the town demanded that money right now if we had these funds held up we wouldn’t be able to pay for that.”
No one on the selectboard disagreed with the recommendations.
Looking further down the road, Fairfax’s contractor for the upgraded wastewater plant, Aldrich & Elliot, is prepared to give a presentation to the board on options coming ahead. The upgrades are expected to cost about $2.5 million, though the town has already secured at least $2.1 million.
The sewer plant on Hunt Street was first in line for upgrades in 2024, after the town received federal dollars to move forward with age-related upgrades on the plant built in the ‘80s. Since then, however, the town discovered the facility has faced decades of mismanagement and neglect with incomplete reporting, testing and cleaning leading to a state investigation.
The presentation will take 40-to-45 minutes, and Bishop said it will take at least two meetings before the selectboard is able to fully weigh the options and come to a decision.
The selectboard is looking at a Sept. 2 or Sept. 16 meeting for the presentation.
Last month, Fairfax’s selectboard approved ordinances which set new rates for uses for the utilities. Per state statute, the town is required to post the ordinances in public areas for a 60-day period. Someone has since taken down four of five ordinances hung around town.
“Apparently, someone decided to go and take them down,” Bishop said. “So my question tonight really is how much time do you want me spending on these sorts of games or politics?”
Before Monday’s meeting, Bishop said water and sewer budgets took a $300 hit because he had to reach out to the town attorney to make sure Fairfax was still in compliance, even though their postings were ripped down.
In one case, Bishop said the ordinance was in a locked case, but someone came in and said they were “with the town” and wanted them taken down.
The town has since put back up the postings.
Since passing the ordinances, Bishop said the town has continued to receive calls from people who have no residential or commercial properties on either utility who are asking questions and are requesting records and files through the Freedom of Information Act.
“It does take up a lot of our time. It’s taking up a lot of our staff time,” Bishop said. “Eventually, I’m thinking of creating a log that will list who’s calling up and asking questions and how much it may be costing the users.”
The legal line item on the utility budgets is not huge, he continued, but every task which requires them to go back to the town attorney is adding to the cost users have to experience.
“This is just really frustrating as a member of a public board that takes a lot of criticism for trying to do the right thing for this town. This is the kind of stuff we have to spend our energy and time on,” Selectboard Chair Lauri Fisher said. “This is just frustrating to me … I hope the paper cut was worth it. Don’t spend any more time on it in my opinion.”