Fairfax awarded $825,000 for wastewater upgrades

Posted

FAIRFAX – After receiving $825,000 from federal sources, the Town of Fairfax is moving forward with age-related upgrades to its wastewater treatment facility.

Located on Hunt Street, the aerated lagoon system in Fairfax was installed in 1980 and today serves 452 households in Fairfax. Town Manager Sarah Hadd said the federal dollars will allow the town to provide updates to the lagoon’s filtration systems as well as to potentially add capacity as Fairfax continues to grow. 

The $825,000 was secured through Vermont’s congressional delegation, along with $30 million for other housing and infrastructure projects throughout the state.

“Federal funds can help jump-start projects that make a big difference in the community—from improving our water infrastructure systems, to building affordable housing, to making a beloved public library more accessible for everyone,” Sen. Peter Welch said in a statement.

Construction is estimated to begin sometime next summer.

Due for an upgrade

As the fastest growing town in Franklin County, Fairfax is wrestling with the need for additional water capacity to deal with population growth, and the town has been pursuing multiple concurrent projects to upgrade its water infrastructure throughout Fairfax.

The $825,000 provided by federal sources should help cover the majority of the cost needed to complete the upgrades at the town’s Hunt Street wastewater facility. Hadd said the town completed a systemwide assessment back in 2021 to identify potential linchpins in the town’s wastewater system, and with money in hand, they can move forward with the final engineering design for upgrades to the 44-year-old facility.

“Because the whole system was built at the same time, we’re running into issues with pump stations. We’re running into a variety of different things. It’s not just the plant, but the sort of infrastructure in bringing wastewater down and through the plant,” Hadd said.

The exact cost of the facility’s upgrades have yet to be determined, but the $825,000 should help cover the final engineering costs, as well as a portion of construction. Fairfax will also be using just under $200,000 from its American Rescue Plan Act funds to complete the 20% match required for the federal dollars.

Using both pools of federal money should help reduce impacts felt by the system’s ratepayers, Hadd said.

“It decreases costs to the user,” she said. “If we’re not able to maintain our wastewater treatment facility, that is a larger concern for the community. It’s not just users who benefit, and we’re able to do more with economic growth.”

The town received roughly $1.4 million in ARPA dollars. Hadd said the funds have been designated to cover the costs of multiple projects, including digitizing town documents, after the selectboard received public feedback on the fund’s expected use.

As for the treatment facility’s exact upgrades, Hadd said engineers are still taking a holistic look at the town’s system to better understand the best approach for construction.

One variable, for example, that could change the final design is how Runamok Maple fits into the large system, Hadd said. Thanks to a federal grant received by the company last year,  Runamok Maple completed the buildout of an expanded filtration system on location to deal with agricultural waste created from their maple-involved production process.

That project could change what Fairfax needs to do with its own wastewater infrastructure, and it could even open up the possibility of adding treatment capacity to its aerated lagoon system depending on Runamok’s impact. Until more info is known though, Fairfax will have to wait and see.

“They give us the ability to rethink the scope of it,” Hadd said.

Searching for water

While moving forward with wastewater improvements, Fairfax also has been looking at expanding its water capacities by trying to find a secondary water source near the town’s existing water access point near Fletcher Road. 

Fairfax Wastewater Superintendent Randy DeVine gave an update to the selectboard of the project Monday, explaining the town has been unable to identify a functioning water source after drilling six wells near the Wheezy Way well in order to locate the needed water pressure. 

After those test wells ran dry, DeVine recommended Fairfax start looking in a different spot, preferably downstream somewhere on the other side of town. That way, the line should help add redundancy to the system should the first water source fail.

To make it happen, DeVine told the selectboard it could be worth bringing in a specialized hydrogeologist to better identify the best spots to drill as the town continues its efforts. 

“We haven’t had much luck but we’ve come up with a few ideas,” DeVine said Monday. “We’re moving forward. Progress is being made.” 

Fairfax’s current water system supplies the town with roughly 40,000 gallons per day, to serve 316 households and businesses.

Comments

No comments on this item Please log in to comment by clicking here