Construction continues at BFA-Fairfax as school set to start

Posted

FAIRFAX – As the first day of school approaches, not only are BFA-Fairfax teachers and staff preparing for students’ return, but construction crews are too. 

When students return for their first day Aug. 26, the school will show clear signs of continued construction activity, but all areas students will access will meet fire and safety codes. Students will also be separated from ongoing construction activity.

The entire $36 million renovation project, approved by voters in January 2023, kicked off this past spring and a ceremonial groundbreaking took place in June. The project includes the construction of three new wings to support more classrooms, a redesigned entryway for the middle and high school, and revamped STEM classrooms and laboratories. 

John Tague, superintendent of the Franklin West Supervisory Union, said construction is speeding up to try and make the first day of school seamless and easy for parents and students. 

During non-school hours, construction will continue on the new wings so as not to disrupt the students. 

“Any construction while students are present will be the additions which will be outside of the school,” Tauge said. “The idea is that the work being done is away from where students are learning.”

This fall, parking spaces at the school will be limited because of the construction, therefore, bus routes and pick-up/drop-off procedures will be updated for the year. 

Tauge said D.E.W. Construction’s staging areas are right in front of the main office and library. This makes about 40 parking spots inaccessible for staff, students and parents. Because more Fairfax students are riding the bus, Tauge said there will be fewer people parking to walk their kid into the building. 

“We have increased ridership on our buses which is a good thing,” he said. “We just needed to reconfigure drop off for elementary, middle and high school for efficiency and it’s going to be the case where parents are going to be asked to drop kids off, not park and walk kids in. This will be a noticeable difference as students come back to school.” 

Construction crews are working through the coming weeks including some evenings as they can’t work safely with additional people in the building. Because of this, the school will hold no back-to-school events before the first day of school. 

Over the summer, sprinklers were installed in the elementary school, the high school and middle school lobby was demolished and hallway ceilings were removed throughout the building.  

The library remodel will continue over the next few months, as the goal is to have the Fairfax Community Library move back in October. Once completed, the public library will remain open at the school while construction continues. 

Steel for the new additions will arrive around the beginning of the school year. Tauge said seeing the new wings come to life is exciting. If someone was to drive by now they can see the foundations, but they can’t tell the work that’s happening inside. 

“When they get the feel for the additions, it will be very visible and I think that it’s exciting to see the progress being made,” Tauge said. “People can actually see the progress on the project.”

The next major phase of construction will begin in March 2025 when the new wings are completed. 

By the end of the project, BFA-Fairfax’s campus will have nine new classrooms added by a two story addition, a new middle school art and make space, increased space for special education services, an enlarged band/choir room and new lighting as well as other renovations.