ST. ALBANS TOWN — A boat ramp or a community center? What do St. Albans Town residents want?
Last week, the Town of St. Albans Selectboard got more information about ongoing work to determine the next big project to reform its old public works property.
But the question still remains: Should the site be a boat ramp or a community center? And how will it affect St. Albans Bay?
After wrapping construction on its new Department of Public Works building in 2020, the town’s former garage – located on 398 Georgia Shore Road – has mostly sat empty. Town administration, however, has been determining ways to change that.
Town planners have been coordinating with engineering firm VHB since October 2023 to collect site information and create possible alternate visions, and three potential ideas were rolled out that following March. They included a dedicated boat launch, a green space and a community center.
During the selectboard’s meeting held this past Wednesday, however, planners re-introduced the three alternatives with additional details around the expected costs of each project to get guidance before filing their final report.
By the end of the conversation, two options remained in the mix. After hearing a presentation by Planning Commission Chair Sarah Hadd on the alternative visions for the site, the selectboard quickly scrapped the idea of a green space/large playground at that location, primarily due to the proximity of St. Albans Bay Park.
That leaves the boat dock and community center options still in play, community development director Megan Sherlund said, and the town will be taking a final look at the two alternatives before closing out the bay’s master plan with engineering consultants.
“VHB will take the two alternatives, put them together in a final plan and close out this portion of the project to identify the best uses, which was the main goal of this master plan,” Sherlund said.
The final say on what gets built at the former DPW site will likely be decided by the Town of St. Albans Selectboard, and right now, Sherlund said the group’s preferred alternative is a boat launch at the site.
Selectboard Chair Jonathon Giroux said he’s heard from other people in the community who support the idea, as an additional access point would help deal with high traffic often seen at Hathaway Point.
The board also raised concerns about the costs associated with maintaining multiple buildings if it moves forward with turning the former salt shed into a community center, especially with the Stone House on the to-do list.
“We’re obligated to do something with (the Stone House),” Giroux said.
The difficulty with a boat launch, however, is engineers still need to figure out if a large-scale one is possible at the proposed site, Sherlund said. Allowing motor boat access to the lake requires a particular depth near the shoreline, although the town has already begun working with the U.S. Army Corps of Engineers to figure out the plan’s viability.
“With the depth of the lake in this area, it would need to be dredged out so the boats could properly float and take off from the area. They’re questions of state permitting and for the Army Corps of Engineers and what kind of mitigation is needed,” Sherlund said.
Early project estimates put the cost to build the boat launch at $1.6 million, although that number could go up depending on what the town would need to do to prepare the ramp, Sherlund said.
As for the second alternative – the community center – the project tended to be preferred by planning committee members. Using roughly $3.6 million, the project would also rehabilitate the old salt storage shed on the site
Commission member Nakuma Palczewski pointed out that the town residents don’t have a community hub to meet like city residents do at Hard’Ack, and the addition could be somewhere where people could meet or hold classes.
Much of the discussion, however, revolved around how much use each asset would get, with most agreeing that the boat launch would get a lot of traffic if Hathaway Point’s busyness is any indication.
At the same time, not everyone owns a boat, selectboard member Amanda Headley said. She had served on the planning commission before getting appointed to the selectboard this past December.
“If there’s more people that would use a community center, I think we should move forward with that,” she said.
In the meantime, the town will continue to pull in information about the project. Sherlund said the town expects to present the final master plan in May for the selectboard’s consideration.
“We’ve selected two possibilities for that property to make it more usable by the public and we are, as a town, diving into the specific expectations and ability for both of those options to happen,” Sherlund said.
The Town of St. Albans did release a survey in February 2019 regarding the use of the former public works site. At the time, 53% of the total 469 respondents wanted the town to develop the site for recreational use, with roughly 84 people communicating they’d like a boat launch on the site. Other high frequency answers include a “park,” “boat/watersport rentals,” “event center/venue,” “picnic area” and “walking paths.”
Comments
No comments on this item Please log in to comment by clicking here