HIGHGATE — The Town of Highgate got more information about the future of its village core project in the form of a water feasibility study this past January.
As a result, the town is now examining the potentiality of a $14 million public water system. No final decision has been made on moving forward with the buildout, but the need for water has major repercussions on Highgate's village core.
Starting in 2017, Highgate town officials began exploring the possibility of a shared wastewater system in order to boost downtown development and create a “village core” for Highgate Center after residents expressed the need for senior housing.
As the project nears a decade in-progress, the wastewater treatment system is almost ready to start construction. But now there’s a new hiccup. The project doesn’t have water.
That fact came to the forefront this past January when Highgate received its water feasibility study back from engineering firm Aldrich & Elliot. After taking a look at potential sources of water in the area, it turns out Highgate could be looking at a multi-year effort of creating its own water utility to serve the village core.
The Highgate Selectboard discussed the issue during its Jan. 8 meeting, where members made the decision to move forward with exploring the cheapest option presented. According to the report, that would be finding a new water source near the village center. Construction of a water system to serve Highgate, however, would be roughly $14 million.
During the discussion, the Highgate Selectboard expressed its concerns about the project as it continues to complicate. As selectboard member Richard Flint explained, the assumption at the start of the project was that any infrastructure buildout could be served by Highgate Arena’s water source, but it turns out that there’s two impediments for that plan.
The first is that the Highgate Arena well isn’t permitted for the water flow necessary, so they’d need to upgrade it to a public system anyway. And Vermont law requires that there be 200 feet of clearance around any intake point in order to cut down on contamination risks.
That rule limits where a well could be placed for Highgate. Aldrich & Elliot, however, identified at least one option on the table – a field just north of the arena owned by the schools that could house a viable well and treatment system.
The full buildout would create a public water system for Highgate with underground lines stretching along St. Armand Road, Gore Road, Route 78 and Lamkin Street.
After the discussion, the selectboard voted to allow the town administrator Fredi Hayes to start exploring the option. The first thing would be to make sure the property could actually support a system, which is still an unknown variable.
The idea that Highgate would also need a public water system for its village core project was unwelcome news for selectboard members and meeting attendees, especially due to the high price tag.
With that said, engineers did explore other ways for Highgate to access water. One option, for example, examined the possibility of extending the Franklin County Airport water line, which was recently completed and turned over to the Village of Swanton for operation. But the cost estimate of installing an additional 18,000 linear feet up to Highgate came in at $18 million, thanks to the need for multiple pump stations.
Engineers also took a look at using Highgate Elementary School’s water source, as well as the arena’s, but then Vermont’s aforementioned 200-foot rule would kick into effect.
The only remaining option — and the cheapest according to the feasibility study — ended up being the installation of a new system altogether, which would pull any water from a new well and pump it to users, as the town itself sits at too high of an elevation to take advantage of a water tower.
After getting the selectboard’s go-ahead, Hayes said during the board’s Jan. 22 meeting she got approval from MVSD to test the potential of a water source on their land. The flow rate there is still a big question that could determine the project’s viability for a public system.
As for Highgate officials, many expressed reservations about moving too fast on a project if Highgate taxpayers were expected to carry the costs. But then again, if Cathedral Square is to create senior housing at the village core, they need to proceed.
“I don’t buy milking equipment, if I don’t have the cows,” Flint said. “But we need water before we do anything.”
The delay caused by needing to build out of a new system also puts pressure on Cathedral Square, which relies on a mix of public and private funding to construct its senior housing. Nonprofit developer Cindy Reid was in the audience on Jan. 8 to explain the disruption puts Cathedral Square in a unique position, but she expects any funds raised by the nonprofit will be able to fulfill their part of the buildout when it comes time.
A lot still needs to happen, however, before Highgate residents can expect to see senior housing on the site.
Efforts to begin brownfield remediation and start construction on the wastewater system — a 20,000 gallon capacity leach field and its associated infrastructure — are ongoing. If all goes according to plan, construction on the wastewater system is scheduled to begin by this fall, and Highgate is currently working out contracts around removing any affected dirt caused by the Machia property demolition to be ready for the build.
As for costs to taxpayers, it’s hard to say. Brownfield work and water projects are often carried heavily by state and federal grants, Hayes said. Also, many utilities are kept in separate funds from a town’s regular operations so users pay much of the costs. At the end of the day, it could be as little as 10% of the costs, although it’s hard to say at this point in the project.
Just this last week, for example, Highgate was able to secure $750,000 via congressionally-directed spending, thanks to Rep. Becca Balint, which will help cover costs associated with the wastewater treatment facility.
As Hayes reminded the board, while the village core project itself has repeatedly been supported by voters in the past, state and federal actors have public safety concerns from grouping too many septic tanks in one area, due to the potential of cascading failures and contamination.
Highgate has also received a lot of interest from businesses about attaching to the new system, which could lead to expanded commercial and economic development.