SWANTON – As Swanton Village moves forward with its downtown transformation project, rising inflationary costs have created a funding gap of $384,000 that village trustees are hoping Swanton Town will help fill.
During a recent joint meeting between town and village officials, Swanton Village’s administrative staff explained the problem, which landed on the village’s desk after they got updated estimates on project costs.
“The very candid conversation here is we need your help,” Village Manager Bill Sheets told Swanton town officials. “A vibrant downtown is key to the community, and what we’re dealing with right now is what every project is dealing with.”
By the end of the meeting, the Swanton Selectboard made no official decision, but board members did express early support for the idea.
“We’ve got to look at this as a return on investment after we’ve got the local option tax,” selectboard member Earl Fournier said.”(Downtown sidewalks) have been neglected for a long time and these improvements need to be made.”
While the latest cost estimates arrived earlier this month, Sheets reminded the selectboard that Swanton’s downtown transformation project – comprising four sidewalk and stormwater improvement projects packaged together – began back in 2015 when the Vermont Council on Rural Development got the conversation going on what Swanton needed for the future.
Since that time, project organizers have been pulling in various funding sources to make the project happen and secured a few federal grants in the process.
The latest estimates, however, have stretched the overall project past its initial $3 million budget. While taking a closer look at updated costs for the “Transportation Transformation” project, the village recently learned that the grants – consisting of three Transportation Alternatives Program grants paired with a Northern Borders Regional Commission federal grant – will likely need an injection of funds to move forward.
To make up for the gap, Swanton Village officials have already dedicated $357,000 toward the grant match. If the project moves forward as planned, village trustees are requesting an additional $384,000 from the town to get it done, Sheets explained.
By the village’s estimate, the funding gaps for all three federal grants total over $800,000, but in-kind donations and the previous match dollars from the village would cover a substantial portion.
If the town commits its funds, the project would then have the dollars necessary for sidewalk improvements along Merchant’s Row and Canada Street, as well as two substantial stormwater upgrades for the system under-and-around Church Street, which includes a new nearby parking lot.
After Sheets explained the overarching funding issue to the selectboard, village grant specialist Heidi Britch-Valenta presented three potential avenues to consider as options. To help the village, the town selectboard could find the funds to move forward as planned, reduce the project by scaling down the Canada Street portion, or cancel the work altogether.
Removing Canada Street from the project, for example, would effectively reduce the shortfall, although the village would still need to raise $94,000. The Canada Street sidewalk upgrade could then be completed as the village finds the funds.
Town officials, however, seemed to be leaning toward finding the funds to complete the whole project, with a few selectboard members offering the local option tax as a possibility to lessen any property tax impacts. If completed, officials said the project would support economic development in the area, as well as buffer downtown safety, especially for pedestrians and cyclists traveling through the area.
Selectboard chair Joel Clark, for example, agreed that there are likely a few things that could be done to improve the village green, like installing a new flagpole and improving sidewalks.
But he was hesitant about giving any final answer Wednesday night, requesting more information from the village about the project. Either way, he expects that it’ll require close discussion between the town and village to better determine how they’d like to proceed.
Selectboard Vice-Chair Nicholas Brosseau also reminded the selectboard about ongoing town efforts to develop a new recreation building. Details are still emerging about the project.
In comparison, Fournier wanted to ask voters about their approach, and he recommended that the board make the request on Town Meeting Day before the board offers its LOT funds. Either way, the both selectboard members and village trustees expect to hammer out a more formalized agreement before moving too far forward, although the clock is ticking.
The Northern Border Regional Commission grant – which is functioning as the funding lynchpin to secure the other three federal grants – needs some guarantee that the village and town are committed to paying for their portion of project costs, Sheets said, within the next year.
The current timeline being considered by Swanton Village estimates construction on the Merchants Row sidewalk and ADA-ramp upgrades could start by next summer, with the majority of the downtown renovation work to be wrapped by 2029.
If all goes forward without any more major hiccups, Sheets said village staff are currently moving through the easement process together with the state planners, with the earliest they’re prepared to go out to bid by next spring.