Trustees make electric decisions

Posted

ENOSBURG FALLS — The village board made two electric decisions on Aug. 14.

Board members approved motions to purchase a new variable frequency drive for the village water department’s well pump, potentially cutting the department’s annual electric bill by $2,000, and a crucial battery charger for the village’s renovated hydro facilities.

The pump in the village’s second well burned out in July, after more than 25 years of operation.

Gary Denton, the village’s public works director, told the board at its Aug. 14 meeting that village workers consistently over-greased the motor, which, consequently, burned off its linings.

But Denton said repeated issues with the motor also led the water department to adjust the pump speed with its valve, straining the motor in a way Denton compared to “driving your car with the parking brake on.”

Denton urged the board to purchase a variable frequency drive for the well’s 30-horsepower replacement motor. The variable frequency drive allows workers to entirely open the valve while automatically adjusting the motor’s speed, rather than straining the valve to adjust the water flow.

Denton predicted the motor could last longer with a variable frequency drive. He also told the board Efficiency Vermont, a non-profit energy savings group, predicted a variable frequency drive could cut $2,000 per year from the water department’s electric bill.

With that in mind, Village Manager Jon Elwell said the $8,551 variable frequency drive could pay itself off in four and a half years. Elwell said those funds could come from the water department’s equipment savings account, which he said had a $22,000 balance.

Not anymore. The board unanimously approved a motion to purchase the drive, without further discussion.

Sam Vaillancourt, a village trustee, did inquire about the condition of the valve. Denton said the valve is “fine,” and noted that without the drive, if the village continued straining that valve, its replacement cost is $5,000.

That’s no longer an issue.

The board also unanimously approved a motion to purchase a 48-volt DC charger, which Elwell said was tangentially tied to the ongoing renovation of the village’s central hydro plant.

Elwell told the board the charger is crucial for the renovated hydro facility to run at maximum efficiency. But its purchase is outside the scope of work detailed in the village’s contract with Kingsbury Inc., the renovator. Elwell said Kingsbury mentioned the need for the charger “a couple of months” ago, and that Elwell and Kingsbury had reviewed supplier quotes in the meantime.

Elwell recommended purchasing the charger from Olsen Electric at a cost of $6,742. Denton said replacing the hydro facilities’ old charger with a used one would cost $4,000, and that buying a new one made more sense.

Elwell said the village would purchase the charger using money from the electric department’s equipment purchase fund, a meager portion of its $92,000 balance.

All this was retroactive. Olsen Electric has a four-week turnaround for the charger order, and the village contractually bound Kingsbury to be substantially done by Aug. 31. Kingsbury has since told the village its work will be delayed, as reported in Monday’s Messenger.

With the Aug. 31 completion date and four-week turnaround in mind, Elwell told the board he sought board chair Walter Scott’s approval to purchase the charger two weeks ago, then did so.

“We were running right up against the time limit of when the project was contracted to be completed,” Elwell told the board.

No one objected. Vaillancourt, again, asked if the village could pay for the charger with the renovation project’s contingency fund, but Elwell said only $5,000 remains in that fund, and “We’re not done with this project yet.”

The board unanimously, and retroactively, approved the purchase.

 

 