ST. ALBANS TOWN – A site plan for St. Albans Town’s proposed new garage was brought before the town’s development review board (DRB) Thursday night, providing the DRB with their first look at the 6-acre facility planned for town property on Brigham Road.
Before a development project – even one spearheaded by the town – can be built, a town’s DRB must approve the project based on criteria established in a town’s zoning laws.
The DRB has not issued a decision on the town garage as of publication. They have 30 days following the conclusion of last night’s hearing to decide on the town’s application.
If approved by voters on Town Meeting Day, the construction of a new garage would relocate the town’s Dept. of Public Works from its cramped lot on St. Albans Bay to a larger facility more centrally located on town property along Brigham Road.
The new garage and its accompanying infrastructure would be spread out over 6-acres of a 73-acre lot owned by the town, following an existing driveway on the property that extends beyond the projected site of the garage.
Its access on Brigham Road will be gated, and planted berms made from fill gleaned from the construction site would shield neighbors and the road from the possible light and noise pollution accompanying the day-to-day activities of the Dept. of Public Works.
A southward-facing garage is arranged along the northern ridge of the lot and was proposed to have 11 vehicle bays, office and storage space, and a drive-through wash bay capable of servicing both trucks from the public works department and the St. Albans Town Volunteer Fire Department’s current fleet.
A filling station for the fire department is also planned for the site.
A salt shed, funded largely through a state grant, would sit at the facility’s eastern bounds, separated from the garage. The driveway wrapping around the shed is large enough to accommodate salt trucks that would have to “swing around back and back into the front” of the shed, according to engineer Peter Garceau, the vice president of Cross Consulting Engineers.
St. Albans-based Cross Consulting was contracted to handle the engineering for the town’s garage project.
Sand, meanwhile, will be accessed from another set of doors on the eastern side of the shed.
The site will be landscaped to funnel stormwater runoff through storm drains and grass-lined swales toward a gravel detention pond to the garage’s south, which will filter the stormwater before ultimately directing it toward the ditch along Brigham Road.
Meanwhile, the garage itself slopes northward, toward a 18,270 square foot grassed groundwater recharge area.
Garceau said that the project is not expected to impact any natural features.
A mound system will be installed to handle sewage and wastewater from the site, a departure from the town’s original plan to connect the project to St. Albans City’s wastewater infrastructure.
The town previously applied to the city for permission to connect its town garage project to the city’s municipal water infrastructure. Selectboard chair Bill Nihan had suggested the application as a form of olive branch to the city, which promptly granted the request earlier this year.
“I once heard that it was going to be hooked onto the city,” observed DRB chair Brent Brigham. “That’s gone by the wayside I take it?”
“For right now, it has,” confirmed town manager Carrie Johnson. “It’s a long-term plan, but we believe it’ll take quite a while to achieve that.”
Since the city awarded the allocation, a lawsuit between the town and city over an extraterritorial affiliation fee attached to the city’s wastewater system was resolved in the city’s favor. Judge A. Gregory Rainville ruled that the town didn’t have legal standing to challenge an affiliation fee charged to private landowners in the town s who hook on to the city’s water and wastewater.
His decision cited the city’s approval of wastewater access at the town garage as evidence the town has not been harmed by the city’s wastewater ordinance.
The DRB heard testimony from the proposed site’s neighbors, Danielle and Gordon McLaughlin, whose primary concerns came from light pollution from a new garage and the possibility of water being funneled into their yard from landscaping and septic work at the garage.
Noise, however, was a less pressing issue for them.
“The sound, to me, is the least of my worries,” Danielle said. “I already live next to a railroad track.”
The lighting question was the concern the DRB dwelled on the most over the course of their meeting.
Elaborating on the lighting plan for the site, Garceau and public works director Alan Mashtare explained that there would be down-shielded lights situated around the property, some of which may have to be left on overnight in case the public works department was called in at night.
“If an emergency happens in the middle of the night and I call out the crew, it’d be nice to see,” Mashtare said.
Other lights would be mounted to the garage and could be altered to be motion-activated if need be.
The lights left on overnight might be dispersed around the property to avoid any single strong source of light that could trouble neighbors, Garceau suggested.
Six-foot-high berms are planned for the edges of the property near its neighbors, including the McLaughlins. The town is proposing to plant those berms with cedar hedging that should further block light pollution produced by the garage.
Mashtare said that early morning operations for the public works department, such as plowing during or after a snowstorm, are typically anticipated for the night before, meaning that snowplows will be readied and salt loaded by the time work crews show up at approximately 5 a.m.
“Usually if we have a storm coming in, we have our trucks preloaded and in the shop ready to go,” Mashtare said. “Even if we started at 5, you wouldn’t hear a backup alarm until 7, 7:30 in the morning.”
As for the neighbors’ worries over water running into and pooling on their property, Garceau said that it was unlikely to be a problem due to planned stormwater infrastructure funneling water toward the garage’s retention pond. When the McLaughlins noted that they already have water pooling in their yard, Garceau responded by saying that that situation might even improve for the McLaughlins.
As the DRB’s hearing began winding down, Brigham encouraged the McLaughlins to voice any other concerns they may have for the project going forward.
“Based on our bylaws, they’re not allowed to affect you in any way,” Brigham said.
The replacement garage has been a centerpiece of town politics for much of 2018, with the town’s selectboard billing it as the St. Albans Town’s “number one priority” immediately following the post-Town Meeting Day reformation of the selectboard in March.
The current town garage’s cramped quarters reportedly makes it difficult for the public works department to accommodate the growing needs of the town and can even present safety hazards, Mashtare told the Messenger in a previous tour of the site.
The garage’s place directly on St. Albans Bay also contributes to worries that runoff from the public works department’s daily operations can wash into the bay, contributing to pollution and algal blooms that continue to trouble Lake Champlain.
The bulk of expenses for the project are to be paid for by existing funds raised from the town’s one percent sales tax. Residents are unlikely to see an impact on their property taxes.
The new garage is expected to be ready by January for placement on a Town Meeting Day ballot.
Pending voter approval, construction is slated to begin fall of 2019.