Selectboard puts $369,000 toward capital; Recreation building gets ‘band-aid’

Posted

SWANTON — Facing a few capital projects in the future, the Town Selectboard designated $369,000 of its remaining federal American Rescue Plan Act funds to cover future capital costs.

Like other municipalities, the Town of Swanton had until the end of 2024 to find a use for $1.2 million in federal funds, although new rules give each town more flexibility on how to spend the funds.

With the deadline passed, Town Administrator Brian Savage said most of the special funds will be used to cover costs associated with some of its largest projects, including the development of a recreation center, updates to the fourth street property and library upgrades.

Future capital needs

Like other Vermont municipalities, Swanton Town Selectboard spent the better part of December taking a close look at next year’s budget. During the board’s Dec. 17 meeting, members heard from Missisquoi Valley Rescue, officials with the Swanton Public Library as well the town highway department to start pulling apart next fiscal year’s various needs. 

Similar to other towns, increases in health insurance are already signaling difficult budget discussions, Town Administrator Brian Savage said. 

The board also considered what to do with the remaining $369,000 that the Town of Swanton held in federal funds — now deemed special funds after a change in categorization. The town had already received and designated most of the $1.2 million received via ARPA back in March, but selectboard members this past month discussed in more detail exactly where they wanted to focus their dollars while getting a few project updates.

At the 4th Street property, for example, selectboard chair Joel Clark explained they had hired Atlas Engineering to help them test soils, but they’d likely need another $30,000 to determine how widespread potential contaminants are on the site. 

Without the extra testing, the town wouldn’t be able to hit state safety standards set for brownfields, he said.

“That property is not going to be able to be used until we move forward,” Clark said. “And to me this is one that has the possibility of special funds.”

Clark said engineers ended up finding a few problems with the site, including the presence of vanadium. The next step is to figure out if the chemical is derived from a prior leak, or if it is naturally occurring.

Savage said the small brownfield site had been the location of the former town garage back in the 40s and 50s, as well a coal depot for the Swanton Lumber Company before that. 

By the end of the conversation, selectboard members agreed to set aside $60,000 in federal funds to tackle brownfield testing with another $20,000 earmarked specifically to cover related upgrades to the Lamoille Valley Rail Trail trailhead and $120,000 toward library insulation upgrades.

Eventually, Savage said the hope is to put some sort of recreational asset on the 4th Street property. Until they know what’s in the soil, however, there isn’t much they can do to utilize the plot. Depending on what’s found though, remedial costs could be in the hundreds of thousands.

Recreational assets

While there hasn’t been much public discussion surrounding the Town of Swanton’s proposed recreation building in recent months, Savage confirmed the project is still moving forward. 

As a sort of “band-aid” project in the meantime, the Town did agree to upgrade Swanton Recreation’s Jewett Street building. Construction planned for this spring includes putting in some new windows for the building and opening up space by creating additional storage. 

The selectboard, however, has not ended its plans for a larger recreational building further down the line, Savage said. Instead, the problem this past year had been the timing.

“It has not been forgotten about, but it’s going to be a good sized price tag to put to the voters and given the tax rate increases in the last year and the way things went, the timing was not good,” Savage said.

Savage is referencing the education property tax rate increase seen last year. The 13.8% year-over-year jump likely hampered municipal requests statewide.

As for the town’s proposed recreation building, back in 2023 the Town of Swanton set aside $600,000 to help cover development costs around creating an expanded space for the Swanton Recreation program.

A portion of those dollars have already been spent as the town has worked with an engineering firm to start putting the final plans together for the building, with early schematics laying out an expanded facility at the Swanton ballfields. 

In total, the Town of Swanton has spent $225,000 of its special funds, with the biggest spend going toward development costs associated with the LVRT and Swanton Library. Just over $30,000 has been spent towards the proposed recreation/community center.

#sanl