Infrastructure countywide gets boost after Town Meeting Day; Montgomery, Highgate, Richford tackle water projects

Posted

FRANKLIN COUNTY — After seeing enough yes-votes this Town Meeting Day, rural towns across Franklin County are tackling the next steps in major infrastructure projects.

In Montgomery, the town is entering the final engineering phase of a small wastewater system to serve Montgomery Center while examining a major streetscape upgrade. In Highgate, residents delivered a positive vote to greenlight construction for its village core project. And in Richford, town officials are tackling the replacement of over 1,000 feet of water lines along Golf Course Road after voters approved a $1.1 million bond for the project.

Montgomery

This past week, Montgomery town officials and the town’s engineering team held open office hours to answer any remaining questions from homeowners about the fine details of the town’s wastewater project.

If all goes well, Montgomery should see construction – on multiple fronts – begin in 2025.

Montgomery’s wastewater project coincides with multiple ongoing projects in the small ski town, but the installation of the new infrastructure is likely the largest. Estimated to cost $10.5 million to complete, selectboard chair Charlie Hancock said state and federal agencies have helped the town secure $9.9 million to cover the majority of the final cost as they’ve paid close attention to the project’s feasibility.

“We’ve had amazing support from the state and feds on this project. The state is really trying to push this forward,” Hancock said.

The system itself is expected to utilize a web-like network of underground pipes meant to feed the wastewater from each household to a “leach field on steroids.” From the outside, Hancock said the subsurface drip dispersal site needed for the new infrastructure would essentially look like a field, as all the treatment would happen below ground and out of sight.

Officials had been planning to create a second wastewater system for Montgomery village residents, but the project fell through this past November when the town wasn’t able to secure the low-lying land necessary for the dispersal site.

If the town should end up with the property down the road, Hancock said much of the preliminary work for the project has already been completed, allowing for future town officials to re-initiate the work if the status quo shifts.

“After failing to secure that location, we’re not able to find a viable alternative,” Hancock said. “If the town wants to pick it back up, the foundation is there to work from.”

As for the Montgomery Center system, Montgomery residents will likely see some construction begin next year. Hancock estimates that by the spring of 2025, the first primary water mains will be installed, followed by the lateral connections to households in 2026. The system itself – designed for over 40,000 gallons per day – is expected to go live later that year.

“I think the state is looking for success,” Hancock said. “A lot of these projects have stalled for whatever reason, and they’re looking for opportunities to get it done.”

Meanwhile, Montgomery is also in planning stages to update its streetscape, and residents provided the vote needed to tear down its old town hall during Town Meeting Day.

The streetscape project initiated by Montgomery would add and upgrade sidewalks along state Route 118 down to the recreation center after the town received $1 million from the Northern Border Regional Commission.

The old town hall property – 98 Main St. – is tied to those plans, Hancock said. Residents denied a motion to restore the old building this past Town Meeting Day, allowing the town to move forward with plans to demolish the building and install a 28-space parking lot near the site.  TD Bank also agreed to have an ATM kiosk nearby.

Construction for the streetscape project is expected to begin shortly after the first wastewater mains are installed in 2025. 

The final piece of the puzzle is the renovation of the town’s municipal center off of Mountain Road. Hancock said the plans include doubling the size of the Montgomery Public Library building by expanding on its southern side, as well as a refurbishment of the town offices currently located in Montgomery's public safety building. 

Town officials are still working through the planning process to move the project forward, and there’s been no cost identified quite yet. Hancock said the town has already committed its ARPA dollars to help with the town office renovation, and the library will be pursuing grants to complete its project.

The goal, Hancock said, is to avoid borrowing any funds to complete the overhaul.

“Our hope is to be as efficient as possible and eliminate costs. We don’t have a final budget, but we hope we can do it without going back for a bond,” he said.

Town voters already approved one part of the plan. This past Town Meeting Day, residents voted to borrow $250,000 to complete the installation of a fireproof vault for the new town offices. The archival documents held by the town are currently stored in gun safes, and the expanded vault is required by state statute.

“We hope that we'll get the final designs done this summer and start construction next year,” Hancock said. “That’s the optimistic timeline.”

Highgate

Highgate residents approved two initiatives related to the town’s ongoing village core project. Both Article 7 – the vote approving construction for a new wastewater system – and Article 8 – selling an acre of village core property to senior housing developer Cathedral Square – passed after a discussion on Town Meeting Day. 

After obtaining the property necessary for the village core’s associated wastewater project in 2024, Highgate is now waiting for additional brownfield and permitting work before moving forward with the system’s final engineering design. Town Administrator Sharon Bousquet said she hopes to have all the necessary documentation in place by 2025, although there’s still a high hurdle in Act 250 before any shovel hits dirt.

In the meantime, the Town of Highgate is planning on holding a joint public hearing with Cathedral Square as the nonprofit assembles the state grants that make up a portion of the funding stack needed for a 30-unit apartment building in the village core. Bousquet said the hearing – scheduled for 6 p.m. on April 4 to be held at the town offices – helps show Vermont Community Development grantors that the project has support.

While work for the village core project continues, the extension of water and wastewater service to Franklin County State Airport just went out to bid this week, Bousquet said, as construction is expected later this year.

Richford

After Richford voters approved a $1.1 million bond to replace a water line along Golf Course Road, town officials are now moving ahead with the project to help restore water pressure in the area.

Jeremy Wiegand, the chief operator at Richford’s water treatment plant, said the project is part of a state-led initiative to improve water services in the area, as the current water pressure available along Golf Course Road doesn’t always succeed in pushing the water up the hill. 

To help, a new booster pump station is expected to be installed near Barnett Monument Cemetery to increase water pressure in the area. Over 2,000 feet of lines are also expected to be replaced to improve functionality and reduce breaks.

Wiegand said the current water line going up the hill utilizes a 2-inch PVC pipe that’s more typical of indoor plumbing. The new lines would be expanded to four-inch and eight-inch water mains.

The replacement extends along Golf Course Road between Province Street and Barnett Monument Cemetery, and construction is expected to begin in 2025 following the bid process to be completed this summer.

Ratepayers are expected to cover 50% of the total costs of the project, which equates to roughly $18.49 per year over a 40-year term for each household using Richford’s water services.