SWANTON VILLAGE — Contractors are finally installing the Orman Croft Hydroelectric Plant’s new dam more than a year after its predecessor’s surprise deflation.
The dam is essentially a massive rubber bag. The last bag deflated on June 14, 2017, due to a previously unseen lesion in its rubber. State inspectors had given the dam a passing grade shortly before its deflation.
Village officials moved swiftly to replace the dam after its deflation. Replacement efforts were already in place prior to the deflation. The dam had reached the end of its roughly 25-year lifespan and the village board of trustees had already resolved to replace the dam in 2018.
Just days before the dam deflated, board members were working out the specifics of doing so in a meeting, ironically, at the hydro plant.
Those preliminary discussions gave officials a slight head start in reacting to the deflation, specifically negotiating to get a replacement bag in half the usual six-month production time.
With promises from the bag’s manufacturer, HTE, and without any regulatory snags, village officials planned to install the dam in October.
Two things got in the way.
One was HTE. Though an American company, HTE’s manufacturing is based in China.
HTE delayed shipping the dam twice. Just before the dam’s scheduled delivery the second week of October, company representatives informed village manager Reg Beliveau Jr. the company would delay the shipment until November, without any reason given for the delay.
For more on the dam issue, pick up a copy of Tuesday’s Messenger or subscribe to our digital edition.