ENOSBURG FALLS – After more than a century and decades in disrepair, Enosburg’s Trout Brook Reservoir Dam is coming down for smaller beaver dams to take its place.
Spearheading the removal and restoration of the grounds is the Franklin County Natural Resource Conservation District. The district has been working on the project since 2022 when it found removing the village-owned dam could have beneficial impacts.
“I think that this is a really exciting project because it is designed to improve the water quality of Trout Brook and lower the temperatures in the stream, which will hopefully improve habitat for brook trout again,” Lauren Weston, FCNRCD district manager, said.
Actual removal of the concrete dam started in August and is expected to continue into the fall. The Trout Brook Dam is only the second the conservation district has torn down. The first was a privately-owned dam in Berkshire in 2021.
Built in 1924, the 16-foot high by 128-foot long dam was built by the Village of Enosburg Falls to be the water supply of the area. It operated for two decades before stopping because it was deemed unsafe for drinking purposes.
Over time, the dam began to degrade and left in a state of disarray as the village moved to dig wells, which it still uses today. That dam — still owned by the village — was slowly becoming a liability for the municipality, Village Manager John Dasaro said.
“The village is just grateful because it's starting to deteriorate and it's only going to be probably a matter of time, so it's kind of one big expense off of the village's plate at some point in the future,” he said.
In order to connect both mouths of the brook, however, FCNRCD alongside SLR Consulting and Sloan’s Excavating need to remove about 16,000 cubic yards of sediment and stabilize the floodplain.
Between deteriorating concrete with cracking, spalling and chunks missing, it was time to take the dam down.
“The dam here wasn't being used anymore, but was in disrepair,” Jessica Louisos, senior water resources engineer at SLR, said. “As many of you saw, it didn't take a huge amount of effort for that excavator to kind of knock the top off with a big chunk.”
Using a hydraulic hammer and an excavator, the two machines break up the concrete dam slowly, releasing the held up water behind the wall. In order to make sure the dam doesn’t face a catastrophic failure, it’s important to go slow, Louisos said.
“It has been the methodical process of taking out smaller pieces at a time, letting the water settle, making sure everything is not deteriorating on its own,” she said.
Already, the water level has been lowered by a number of feet, controlling how much sediment will fall into the river. The ponded area before the removal required kayaks to navigate, Weston said.
If the restoration effort had crews just tear down the wall in the fastest way possible, lots of sediment would follow. It would clog culverts and smother forest habitats from the 100 years of build up sediment layers, Louisos said.
The sediment will instead be carried over just down the road to land owned by the village to be leveled out, buried and restored with native vegetation.
The village doesn’t just get a liability off their hands, Dasaro said, the field around the stream will be covered in solar panels. Construction is expected to start in spring.
As the excavation crew slowly lowers the level of the dam, the ponded water at the top has been left to dry and will eventually be seeded with native plants and trees.
“I think it's really easy to see the infrastructure that we see these days, and think it's how it's been for all of time,” Weston said. “But I think having the really detailed documentation of this dam in particular is interesting to know that it's been for only 101 years, and we're helping to restore it back to its former glory.”
But in order to restore the whole stream area, it requires more than just connecting the two sides of the dam, it needs to encourage native species to repopulate the area.
To help that, the excavating crew has taken out the invasive species which took over the area, and begun to create “beaver dam analog” — hand-built structures mimicking a natural beaver dam — through the newly re-exposed floodplain upstream of the dam.
“There's 12 of those structures spanning the whole restoration area. What those do is they kind of serve to stabilize the river a little bit, prevent some resistance to erosion, but also they're really important for habitat,” Louisos said. “We also hope that the beavers will recolonize after construction and kind of use those as a starting point to rebuild some of their dams.”
After the project is complete, the area will have a restored floodplain with added flood storage. The restored stream will connect 4.8 miles of habitat for aquatic animals.
The dam itself originally stood as a barrier for fish passing through the waterway; by removing the concrete structure, fish will be able to freely flow upstream and downstream.
Removal of the dam also creates a more inviting environment for species which haven’t previously seen strong numbers in the waterway, like brook trout.
“With the dam in place, there's this stagnant pond upstream, or there was, and that raises water temperatures in the stream, which makes it less suitable for cold water species like brook trout,” Alexandra Marcucci from SLR said.
By removing the dam and planting lots of native vegetation, Marcucci said the hope is stream water temperatures will be reduced to support the native trout population in coming back to the area.
Once the stream has naturalized into a free-flowing path, FCNRCD will plant thousands of trees along the river and in the ponded area that has been cleared, returning the area back to its natural state.