Bridge repair dates set for Swanton B6 bridge; Disruptions in downtown traffic expected July 8 through Aug. 19

Posted

SWANTON — Traffic in downtown Swanton will likely see some snarls this summer, as one of its main overwater thoroughfares – the Veterans Memorial Bridge – will be closed down for repairs.

The bridge closure, scheduled between July 8 and Aug. 19, is expected to give contractors 14 to 20 days to complete repairs. 

The work required includes replacement of the bridge’s slide steel expansion joints that provide the flex necessary to handle heavy traffic loads. 

Due to the breakdown, water leaking through each end of the bridge has also caused the underlying steel beams to further rust and break down, according to a Vermont Agency of Transportation’s status report on the bridge completed last summer.

A full replacement is scheduled for 2029. The bridge was initially built in 1966.

Detours

To handle diverted traffic, the village administration will be directing vehicles to take a five-mile-long detour in order to cross the river at Depot Street. 

The proposed detour will bring motorists down Grand Avenue to cross the Missisquoi River at Swanton’s southeast end, then send cars south down Route 7, before taking them west along Beebe Road and then north up South River Street.

During the village’s May 13 meeting, Swanton residents living along the detour expressed concerns about the increases in speeding traffic along that route, especially on South River Street. 

Current traffic over the bridge is about 10,000 vehicles per day.

Village Manager Bill Sheets said the heightened traffic is definitely on the administration’s radar as it moves forward with the project.

“It’s a collaborative problem. Our police department will be, I promise you, engaged in that effort to slow people down. It’s not going to be 24/7 but certainly during those high peak times,” Sheets said. “There’s going to be so much signage and I think the pace of traffic will necessitate a slowdown.”

The village will also be responsible for marking the route. As a way to help curb $110,000 from the total project costs, Sheets said the administration was able to negotiate with the singular bidder, DirtTech, to bring down the construction costs as a trade for installing signage.

“That’s good news for us, good news for you as taxpayers. Bad news for (public works foreman) Dean Ryan and his crew. It really is,” Sheets said. “So, he’s not loving it, but he’s embracing it.”

The initial bid received by the village came out at $451,000. Reducing the expected costs by $110,000 brings the final costs down within striking distance of state grants. Sheets said the village recently received another $175,000 state grant to round out the $200,000 already in hand to be able to cover the roughly  $375,000 needed for the project. 

The village will also be seeking out a $10,000 grant, Sheets said, in order to pay for two mobile lighting trailers the village can keep after finishing the bridge repairs. 

The equipment will be beneficial to help with other late night repairs associated with the village’s other utilities, he said. 

Looking at 2029

While repairs to the bridge are likely to be completed this summer, VTrans expects to move forward with a full replacement of the Veterans Memorial bridge by 2029.

Details are still sparse about what that will mean exactly for Swanton residents, but the state expects to roll out the first round of information at an upcoming meeting scheduled to start at 7 p.m. June 10 at the Village municipal complex.

At this time, the village has an expected match for the work between 2.5% and 10%. The overall total bridge replacement cost will likely be in the millions of dollars, and the work will likely require a longer shutdown of the river crossing than what’s planned this summer.