ST. ALBANS TOWN — The building at 282 Georgia Shore Road is scheduled to be demolished by the Town of St. Albans next Monday, Dec. 8.
The property was initially purchased for $220,000 by the town in 2023 to make additional room near the five-way intersection on Georgia Shore Road for future improvements. The demolition also widens the egress to the adjacent former public works property.
The Town of St. Albans is currently examining possible improvements to both areas of the bay, although details for both projects are still in the works.
If all goes according to plan, Town Manager Casey Toof said the building – a single-family three-bedroom residence – will be torn down by the St. Albans Town public works department next Monday.
The work itself is being done by town employees after the building was cleared of asbestos and other hazardous materials.
“A company came in and did the asbestos removal. They went right through and all the hazardous materials in that building have been removed, so we’re not worried about contamination,” he said.
The building also doesn’t qualify as a historic property, he said.
As for the property’s final use, Toof said the town is still working through some concepts of how the land will fit into the area’s final configuration, or what the area will look like.
With that said, the town has made some steps to start planning toward those efforts. A bay-wide vision plan published last year, for example, has taken a closer look at the various infrastructure projects that could improve the quality of life in the bay, while a planning study prepared by engineering firm VHB lays out various uses for the former department of public works.
One suggestion to improve that five-way intersection includes closing off Patten Crosby Road’s access to create a four-way intersection, although a new road would need to be built to connect it to Seminary Hill Road to maintain the road network. The second potential option listed by the study explored by town planners would be to create a roundabout at that intersection.
As for the former department of public works property, the Town of St. Albans did look at what to do with that property in 2023 after working with engineering firm VHB. The planning commission then presented their findings to the selectboard back this past February.
Since that time, the selectboard has seemingly made its decision about its preferred option. This fall, the town – while working under Interim Town Manager Corey Parent – sent out a request for qualifications to seek out an engineer knowledgeable about designing boat ramps.
When Parent was asked during public comment in October whether the town would be seeking engineers for anything outside the boat launch option, Parent said he wouldn’t be doing it “without the selectboard’s directive.”
“We’ve had multiple community surveys,” he told resident Zach Green. “We’ve had planning studies and that’s the number one option that the residents have said they want to use that property for.”
The RFQ seeking out engineers asks “respondents … to provide comprehensive documentation demonstrating their firm's capabilities, past project references, and technical approach to designing a functional and compliant boat launch facility.”
The Town of St. Albans did release a community survey in February 2019 regarding the use of the former public works site. At the time, 53% of the total 469 respondents wanted the town to develop the site for recreational use, with roughly 18% of total respondents communicating they’d like a boat launch on the site. Other high frequency answers include a “park,” “boat/watersport rentals,” “event center/venue,” “picnic area” and “walking paths.”
In a video released this fall, selectboard member Amanda Headley questioned how a boat launch might work in the area, showing physically the depth of the shoreline waters by wading out herself into Lake Champlain with a bullhorn to report her results.
Otherwise, since February there’s been no public decision made by the St. Albans Town Selectboard members regarding which option they’d like to pursue.
Town documents estimate the project would cost $1.6 million to complete, while leaving “little room for park use aside from boaters,” according to VHB engineers.
Comments