FRANKLIN COUNTY —  The Vermont Agency of Transportation has deployed its fleet of road signs to warn drivers of upcoming summer projects. 

Here’s the shortlist of what Franklin County drivers can expect as Vermont’s construction season kicks-off.

Route 104 Resurfacing

State Route 104 will see two inches of new pavement added to its pockmarked surface this construction season when the section between Fairfax and its intersection with Route 105 gets an upgrade.

VTrans is scheduled to resurface the 11.7 miles of the state route by milling the road and repaving it. In addition, the project also includes adding a right-turn lane to the I-89 offramp to improve the intersection, as well as resurfacing of the St. Albans State Highway.

The project’s total estimated cost is $4.6 million, according to VTrans. The contractor is Pike Industries, and the work is expected to be completed by this fall.

Relatedly, VTrans also has plans to completely upgrade Exit 19 over the next few years, with early intentions leaning toward the construction of a roundabout.

The project is still in its planning stages, but St. Albans residents will have a chance to give input on the intersection’s future plans during a public hearing at St. Albans Town Education Center cafeteria, planned for 6 to 7:30 p.m. Wednesday, May 15.

Route 105 Resurfacing

VTrans will be resurfacing eight miles of state Route 105 between St. Albans and Sheldon this construction season.

Scheduled to begin April 29, the re-paving project will start at Route 105’s intersection with U.S. Route 7 in St. Albans, extend for eight miles and end in Sheldon.

The estimated cost for the paving project is roughly $4.2 million. Upgrades include milling down the top two inches of roadway and replacing it with new asphalt, as well as installing project guardrails, signage, highway shoulders, ditching, traffic signs and centerline rumble strips. 

The project – contracted to the Frank W. Whitcomb Construction Corporation – also includes updates to the signal infrastructure at the intersection of routes 105 and 104. 

Construction is expected to be completed by this fall.

I-89 south of St. Albans

Both the northbound and southbound lanes on Interstate 89 are also on VTrans’ agenda for 2024. 

Estimated to cost $13.7 million to complete, the interstate repaving project will replace the 11-mile stretch south of Exit 19 in St. Albans to where the interstate crosses the Lamoille River in Milton. 

Since both sides of the interstate are scheduled to be repaved, the project includes a total of 22 miles of work, as well as the repavement of the associated exit ramps. Some guardrail repairs and shoulder work are also expected.

The contractor awarded for the project is Pike Industries. Construction is expected to be completed by the fall of 2024 and last throughout this spring and summer.

Fairfield Bridge Deck Replacement

Fairfield’s bridge on state Route 36 spanning the Fairfield River will be closed for over a month starting this June as construction workers move forward with a deck replacement. 

According to VTrans engineers, the bridge is dealing with cracks, breaks and chipping concrete throughout the deck structure that could prove problematic as the bridge ages. The bridge itself was built in 1955.

VTrans workers will use “accelerated bridge construction techniques” to complete the project in 28 work days. The expected timeline is June 17 to Aug. 23.

The deck replacement will also include a new bridge railing and paving. The total estimated cost is $1.9 million, and the construction bid was awarded to A.L. St. Onge Contractor.

During the construction period extending through the middle of summer, an offsite detour has been established to funnel east and west traffic that usually moves through Route 36. The intended regional detour route listed by VTrans encourages drivers to take routes 105 and 108 for anyone traveling back and forth between St. Albans City and East Fairfield or Bakersfield. 

A local bypass is also available for Fairfield residents at Chester A. Arthur Road, and VTrans provided a $19,655 grant to help with dust control and signage during the closure, according to selectboard meeting minutes from this past February.